Sample output

Sample: Sitework addendum checklist


Static sample only. It shows the shape of the memo, not a real bid review.

ProjectNorth Creek Road Improvements
TradeGeneral / Sitework
AddendumNo. 01
Bid riskHigh
Trade impactHigh
Sources5 source snippets across pages 1-9

Required before bid

  1. Update bid due date to May 28, 2026 at 3:00 PM.
  2. Include signed addendum in the sealed bid package.
  3. Review revised roadway, utility relocation, quantity, and SW3P sheets.
  4. Update estimate for changed excavation, mobilization split, utility items, and insertion valves.

Changes to review

TypeItemDetailSource
Bid dateBid due date changedOriginal due date changed from May 27, 2026 to May 28, 2026.Page 1
AcknowledgmentSigned addendum requiredAddendum must be signed and returned with the bid to avoid disqualification.Page 2
Affected sheetsRoadway and utility relocation sheets revisedMultiple sheets revise quantities, utility relocation items, environmental notes, and SW3P items.Pages 7-9

Source snippets

PageSnippetNote
Page 1
The bid opening date is changed from May 27, 2026 to May 28, 2026 at 3:00 PM local time.
Bid calendar must be updated.
Page 2
This addendum shall be signed by the bidder and included with the sealed bid package.
Missing signature could make the bid nonresponsive.
Page 7
Revised roadway quantity summary updates excavation, embankment, and temporary traffic control quantities.
Quantity takeoff review needed.
Page 8
Utility relocation items are revised to include insertion valves and adjusted waterline connection details.
Utility subcontractor scope may change.
Page 9
SW3P sheets are revised to add inlet protection, stabilized construction entrance details, and environmental notes.
Erosion control pricing should be checked.

Open app|Pilot contact|Connect on LinkedIn

Static sample only. Real project outputs point back to uploaded PDF pages. Not official bid review. Always verify against issued bid documents.